T2S Release 3.2 Status Update No. 1 – Preparation of “T2S Deployment Weekend”
In Announcement D19036 Clearstream Banking AG (CBF) informed customers about the upcoming T2S Release 3.2. The attachments in this Announcement list the T2S Change Requests and Problem tickets that are included in the scope of T2S Release 3.2. The “Indicative timeline for the deployment of T2S Release 3.2” for this weekend (15 to 17 November 2019) was provided in Announcement D19049.
Based on the latest documentation provided by the ECB there will be changes in the T2S Operational Day for the business day Monday, 18 November 2019. All changes will be effective upon completion of the end-of-day procedure for Friday, 15 November 2019.
The “Indicative timeline for the deployment of T2S Release 3.2” was updated to show the latest schedule provided by T2S on Wednesday, 6 November 2019. The final version highlights the changes in comparison to the initial schedule published. Unless otherwise stated, all times are given in Central European Time (CET).
The table below provides an overview of the important milestones of the “T2S Release 3.2 Deployment Weekend” for which Operational News will be published.
Operational News | Milestone | Due date / time (CEST) |
#1 | T2S Release Weekend Schedule | Monday, 11 November 2019 |
#2 | Completion of CBF End of Day Processing | Friday, 15 November 2019, 19:30 |
#3 | Green Light for | Friday, 15 November 2019, 20:00 |
#4 | Start of Transmission (A2A) | Sunday, 17 November 2019, 02:00 |
#5 | Start of Transmission Clearstream Settlement Reporting | Sunday, 17 November 2019, 07:00 |
#6 | Completion of T2S Real-Time-Settlement (RTS) and Start of Maintenance Window | Sunday, 17 November 2019, 11:15 |