Business Continuity Management: Systems unavailability test date - update
Reference
Note: This information originally published on 12 September 2017 was updated with a new timeline. Changes have been highlighted.
It is Clearstream’s philosophy to constantly improve products and services. This also applies to the Business Continuity Management programme. As part of this programme, we will again be offering customers the possibility to participate in our Business Continuity Management (BCM) test planned for
Saturday 30 September 2017
On that day, we shall simulate the unavailability of one of Clearstream’s production data centres. During the course of the test, Clearstream systems will be run in contingency mode, which will apply also to the real-time processing (RTP) period. Customers will have the opportunity to participate in the test between 13:00 and 15:00 (CEST) to validate their connectivity and processing.
All data input during the test will be processed. Normal processing will continue with the RTP period starting at 21:05 (CEST) Sunday 1 October 2017.

In view of the circumstances of the test, all timings quoted here can only be approximate.
Timeline of events
Normal processing | |||
Friday 29.09.17 | 20:00 |
| Both data centres |
Start of test | |||
Saturday 30.09.17 | 07:00 |
| Remaining data centre |
| 13:00 – 15:00 |
| Remaining data centre |
Saturday 30.09.17 | 15:00 |
| Both data centres |
End of test | |||
Sunday 01.10.17 | 21:05 |
| Both data centres |
Customers who would like to participate in the test are kindly asked to provide a contact person that can be reached if necessary. Please indicate the name, telephone, fax and email details of this person.
Customers can also consider using their own backup site.
More information is available in the Questions & Answers document which is provided below for Premium Users only.